Agenda/Minutes are posted at: https://etherpad.openstack.org/p/stx-releases Release Team Meeting - April 2 2020 stx.4.0 - Continue the review of Milestone-2 criteria - Two criteria were already met last week - Spec freexe; no new specs accepted for the release. The focus is on closing current specs - Feature plans defined and feature development well underwa - Focused on reviewing the third criterion - Release tet plan defined - Feature Testing - The majority of features have target dates for test execution with reasonable risk - Key concern/risk is with the Openstack Upversion - Testing currently expected to go into June -- current plan: June 5 - Expect issues and updates to automation test-cases - Regression Testing - Expect to start regression two weeks later and end two weeks later than the orignal plan - This will push the backend of the release by about two weeks as well - New Dates: - Milestone-3: May 29 - Feature Test: Jun 5 - Regression Test: Jun 26 - RC1: Jun 26 - Final Regression: July 10 - Release Date: July 17 - The release team agreed that this is acceptable - Need to monitor that test activities are moving forward as per plan as the team is still working thru a number of h/w dependencies and ramp up - Team agreed to declare MS-2 today -- Congratulations to the whole team!