Hey Haris,

 

Just following up with you, as Rob’s delegate while he’s out,
What is the status of STX 9.0 Release: Regression Test Complete (including Final Regression)   … FCST was March 22 .

 

From STX Meeting:

§  Regression Test Complete (inclduing Final Regression) - Fcst: Feb 28 >> March 6 >> March 22 >> Done ? Update ?

·         Combining the remaining regression testing w/ the final regression on the stx.9.0 branch

·         Sanity has started on stx.9.0; should be done by end of this week ( March 15 )                    - Update ?

·         Some manual regression is in progress ... should be done mid-next-week ( March 20 )      - Update ?

·         Plan to complete automated regression by mid-next-week ( March 20 ) --                             - Update ?

·         Note: There is a risk to the above dates due to lab infrastructure moves

·         Action: Haris to confirm the above regression plan

§  haris did confirm plans last week

·         (march 20) no update ... greg to ping haris on "Regression Test Complete" milestone status on mailing list.

 

let us know,

Greg.