[Starlingx-discuss] Minutes: StarlingX Release Meeting - March 14/2019
Cabrales, Ada
ada.cabrales at intel.com
Thu Mar 14 23:50:19 UTC 2019
Please take a look at my comments below, regarding testing.
A.
> -----Original Message-----
> From: Khalil, Ghada [mailto:Ghada.Khalil at windriver.com]
> Sent: Thursday, March 14, 2019 4:24 PM
> To: starlingx-discuss at lists.starlingx.io
> Subject: [Starlingx-discuss] Minutes: StarlingX Release Meeting - March 14/2019
>
>
> Thank you to all who attended the release sub-project meeting today.
>
> Agenda/Minutes are posted at:
> https://etherpad.openstack.org/p/stx-releases
>
> Release Meeting Agenda/Notes - March 14/2019 Goals for the meeting:
> - Ghada: Review the overall status of the release -- item-by-item as well as
> overall
> - Acknowledge whether the current dates are achievable
> - If not, work on a plan to revise the release dates
> - Bruce: There are people waiting for this release. There is interest by one party
> to deploy StarlingX as an edge device.
> - We need to set a high bar for ourselves
> - We need to have a stable release with the required content
> - Bill: What is the critical path? Which items need more attention and how can
> we bring focus to these items?
>
> Current Dates
> - MS-3: Apr 8-12 2019 / RC1: Apr 29-May 3 2019 / Release: May 20-24 2019
> - Countdown to MS-3 is 4wks
>
> Green -- On Track / Non-Blocking Items
> - CVE Upgrades
> - CentOS upgrade to 7.6
> - Kernel and user-space packages have merged as of March 11
> - ovs-dpdk upversion is in progress: some issues to work through, but we feel
> this can make it
> - Python3 Readiness
> - Prep. Not gating the StarlingX release schedule.
> - Integrate Containerized OVS
> - On track; this should be ready before the current MS-3
> - Non-Openstack Patch Backlog Reduction
> - Best effort; does not gate the StarlingX release schedule
> - Openstack Rebase
> - Most components have been rebased.
> - Final item is to complete the rebase of horizon, keystone, Barbican on the
> host. Fcst: March 30
> - Green for milestone-3
> - DevStack Enablement
> - Not gating the StarlingX release schedule
> - OVS-DPDK Enhancements
> - Small enhancements; this should be ready before the current MS-3
>
> Yellow -- Watch List
> - Documentation
> - 35 stories in play. Not fully staffed currently. Need more community help to
> land this.
> - Still working more detailed plans.
> - On watch to determine what is the minimal set required for the release
> (need to focus on resourcing those items) and what can come after
> - Anisble bootstrap Deployment
> - Preliminary code is available, but facing issues in testing.
> - Status is yellow relative to the current MS-3
> - Anchor feature
> - Ceph Upgrade
> - Need an update from Cindy, but it feels like this is about 1wk past the current
> forecast (Apr 5), so pushes against the current MS-3 date.
>
> Red -- Won't Make the current dates
> - Containers
> - Anchor Feature -- holds up the release
> - 28 stories still open
> - Frank currently working story-by-story on a new forecast
> - Action: Frank - Plan to have a new plan/forecast by March 22
> - Distributed Cloud
> - Anchor Feature -- holds up the release
> - Direct dependency on containers. Got impacted by a late start due to the
> containers cut-over.
> - With the containers cut-over done, we now are able to make progress.
> Dependency is finish-to-finish now.
> - Action: Dariush - Plan to have a new plan/forecast by March 22
> - Distro Openstack Patch Elimination
> - Anchor Feature -- holds up the release
> - Policy is to upstream to train first, then backport to StarlingX
> - Still need to work out timing/plan in terms of reviews being posted and
> stable
> - Need to decide the key items the StarlingX release should be gated on
> - Action: Bruce to figure out plan proposal
> - Not confident we can have a full plan by next week, but will work
> towards a clearer view - especially around the gating items
>
> Test Readiness
> - Test Case Definition is on track
> - Feature Testing (Execution)
> - Action: Ada/Numan to update each feature on the release plan with the
> "Feature Tested" date.
> - For Features where are the dates are being re-worked, wait until next week
> when a new date is available
> - Regression Testing (Execution)
> - Original plan has release regression starting next week
> - However, with the shift in a number of key features, this plan needs to be re-
> examined
> - Options: (1) Delay regression start. (2) Start reduced regression now, but
> plan another regression cycle when anchor features are ready.
>
Based on the stability of the release, I suggest to delay the beginning of regression testing. We haven't had a green sanity since 03/05. We can re-define a date when we have clarity on the delivery of the key features, and continue running Sanity meanwhile.
> Bug Resolution
> - Review in next meeting
> - Need to make sure the new dates provide adequate time for bug resolution.
>
> Conclusion:
> - Current MS-3 is highly unlikely >> knock-on effect to the subsequent release
> milestones as well
> - Next week we will work on proposal for the new date based on revised plans
> for the above items
>
>
> Regards,
> Ghada
>
> _______________________________________________
> Starlingx-discuss mailing list
> Starlingx-discuss at lists.starlingx.io
> http://lists.starlingx.io/cgi-bin/mailman/listinfo/starlingx-discuss
More information about the Starlingx-discuss
mailing list