[Starlingx-discuss] Minutes: StarlingX Release Meeting - March 14/2019

Cabrales, Ada ada.cabrales at intel.com
Thu Mar 14 23:50:19 UTC 2019


Please take a look at my comments below, regarding testing.

A.
> -----Original Message-----
> From: Khalil, Ghada [mailto:Ghada.Khalil at windriver.com]
> Sent: Thursday, March 14, 2019 4:24 PM
> To: starlingx-discuss at lists.starlingx.io
> Subject: [Starlingx-discuss] Minutes: StarlingX Release Meeting - March 14/2019
> 
> 
> Thank you to all who attended the release sub-project meeting today.
> 
> Agenda/Minutes are posted at:
> https://etherpad.openstack.org/p/stx-releases
> 
> Release Meeting Agenda/Notes - March 14/2019 Goals for the meeting:
> - Ghada: Review the overall status of the release -- item-by-item as well as
> overall
>     - Acknowledge whether the current dates are achievable
> - If not, work on a plan to revise the release dates
> - Bruce: There are people waiting for this release. There is interest by one party
> to deploy StarlingX as an edge device.
>     - We need to set a high bar for ourselves
>     - We need to have a stable release with the required content
> - Bill: What is the critical path? Which items need more attention and how can
> we bring focus to these items?
> 
> Current Dates
> - MS-3: Apr 8-12 2019  / RC1:  Apr 29-May 3 2019  / Release: May 20-24 2019
>     - Countdown to MS-3 is 4wks
> 
> Green -- On Track / Non-Blocking Items
> - CVE Upgrades
> - CentOS upgrade to 7.6
>     - Kernel and user-space packages have merged as of March 11
>     - ovs-dpdk upversion is in progress: some issues to work through, but we feel
> this can make it
> - Python3 Readiness
>     - Prep. Not gating the StarlingX release schedule.
> - Integrate Containerized OVS
>     - On track; this should be ready before the current MS-3
> - Non-Openstack Patch Backlog Reduction
>     - Best effort; does not gate the StarlingX release schedule
> - Openstack Rebase
>     - Most components have been rebased.
>     - Final item is to complete the rebase of horizon, keystone, Barbican on the
> host. Fcst: March 30
>     - Green for milestone-3
> - DevStack Enablement
>     - Not gating the StarlingX release schedule
> - OVS-DPDK Enhancements
>     - Small enhancements; this should be ready before the current MS-3
> 
> Yellow -- Watch List
> - Documentation
>     - 35 stories in play. Not fully staffed currently. Need more community help to
> land this.
>     - Still working more detailed plans.
>     - On watch to determine what is the minimal set required for the release
> (need to focus on resourcing those items) and what can come after
> - Anisble bootstrap Deployment
>     - Preliminary code is available, but facing issues in testing.
>     - Status is yellow relative to the current MS-3
>     - Anchor feature
> - Ceph Upgrade
>     - Need an update from Cindy, but it feels like this is about 1wk past the current
> forecast (Apr 5), so pushes against the current MS-3 date.
> 
> Red -- Won't Make the current dates
> - Containers
>     - Anchor Feature -- holds up the release
>     - 28 stories still open
>     - Frank currently working story-by-story on a new forecast
>     - Action: Frank - Plan to have a new plan/forecast by March 22
> - Distributed Cloud
>     - Anchor Feature -- holds up the release
>     - Direct dependency on containers. Got impacted by a late start due to the
> containers cut-over.
>     - With the containers cut-over done, we now are able to make progress.
> Dependency is finish-to-finish now.
>     - Action: Dariush - Plan to have a new plan/forecast by March 22
> - Distro Openstack Patch Elimination
>     - Anchor Feature -- holds up the release
>     - Policy is to upstream to train first, then backport to StarlingX
>     - Still need to work out timing/plan in terms of reviews being posted and
> stable
>     - Need to decide the key items the StarlingX release should be gated on
>     - Action: Bruce to figure out plan proposal
>            - Not confident we can have a full plan by next week, but will work
> towards a clearer view - especially around the gating items
> 
> Test Readiness
> - Test Case Definition is on track
> - Feature Testing (Execution)
>     - Action: Ada/Numan to update each feature on the release plan with the
> "Feature Tested" date.
>     - For Features where are the dates are being re-worked, wait until next week
> when a new date is available
> - Regression Testing (Execution)
>     - Original plan has release regression starting next week
>     - However, with the shift in a number of key features, this plan needs to be re-
> examined
>     - Options: (1) Delay regression start. (2) Start reduced regression now, but
> plan another regression cycle when anchor features are ready.
> 

   Based on the stability of the release, I suggest to delay the beginning of regression testing. We haven't had a green sanity since 03/05. We can re-define a date when we have clarity on the delivery of the key features, and continue running Sanity meanwhile. 



> Bug Resolution
> - Review in next meeting
> - Need to make sure the new dates provide adequate time for bug resolution.
> 
> Conclusion:
> - Current MS-3 is highly unlikely  >> knock-on effect to the subsequent release
> milestones as well
> - Next week we will work on proposal for the new date based on revised plans
> for the above items
> 
> 
> Regards,
> Ghada
> 
> _______________________________________________
> Starlingx-discuss mailing list
> Starlingx-discuss at lists.starlingx.io
> http://lists.starlingx.io/cgi-bin/mailman/listinfo/starlingx-discuss


More information about the Starlingx-discuss mailing list