[Starlingx-discuss] Minutes: StarlingX Release Meeting - Nov 14/2019
Khalil, Ghada
Ghada.Khalil at windriver.com
Mon Nov 18 17:12:44 UTC 2019
** There was no meeting on Nov 14. However, offline comments were added to the etherpad.
Agenda/Minutes are posted at:
https://etherpad.openstack.org/p/stx-releases
Release Team Meeting - November 14 2019
** Meeting is cancelled. Request for offline updates are per below **
stx.3.0
- Feature Status
- https://docs.google.com/spreadsheets/d/1ZFR-9-riwhIwiBYBmWmi1qOVyHtgJ8Xk_FaF2jp5rY0/edit#gid=1010323020
- Upversion to train
- Still working thru docker image issues >> Addressed as of Nov 15
- Wait until official sanity with train is done to declare Milestone-3
- Distributed Cloud
- Testing is complete
- Fault Containerization
- Ada to confirm that the re-test is done
- Ada: Testing is complete, will investigate extra task https requested by Yang
- Intel GPU support for K8s
- Feature is done. Ran working on one enhancement that is not considered gating.
- Cindy/Frank to ask developer to send doc info
- Ada to provide an update on the re-test as discussed
- Ada: This feature is going to be retested along with Train upgrade testing
- Intel QAT support for K8s
- Feature is done.
- Cindy/Frank to ask developer to send doc into
- Ada to provide an update on the re-test as discussed
- Ada: This feature is going to be retested along with Train upgrade testing
- Regression Test
- https://docs.google.com/spreadsheets/d/1X085xI96M6PIeum87w6IEF11G-TG-W1OeGuAJWnrAWI/edit#gid=1717644237
- Completion Rate: 49% (up from 44%)
- Ada to update with status, completion date, any risks, etc
- Since we are waiting for the Train ISO. we are going to execute all the TC planned in : https://docs.google.com/spreadsheets/d/1X085xI96M6PIeum87w6IEF11G-TG-W1OeGuAJWnrAWI/edit#gid=1691167242
- This testing includes 100 Pytest TC + 100 Robot TC + 75 Test cases from feature testing (manual execution), and will try to cover fixed bugs. Goal , to be completed on 11/29
- Once that we got the RC ISO we are going to start with a new Test Plan that Elio and Yang will provide + Remaining TC from first cycle that weren't executed. To be compeleted on 12/13
- Feature Test
- https://docs.google.com/spreadsheets/d/1n9P7as4iqO55DytIRuIGdyc7x0n2WM_q-cMfHcItJlY/edit#gid=968103774
- Completion Rate: 100% (up from 85%)
More information about the Starlingx-discuss
mailing list