[Starlingx-discuss] Minutes: StarlingX Release Meeting - Nov 14/2019

Khalil, Ghada Ghada.Khalil at windriver.com
Mon Nov 18 17:12:44 UTC 2019


** There was no meeting on Nov 14. However, offline comments were added to the etherpad.

Agenda/Minutes are posted at:
https://etherpad.openstack.org/p/stx-releases 


Release Team Meeting - November 14 2019
** Meeting is cancelled.  Request for offline updates are per below **
stx.3.0
- Feature Status
        - https://docs.google.com/spreadsheets/d/1ZFR-9-riwhIwiBYBmWmi1qOVyHtgJ8Xk_FaF2jp5rY0/edit#gid=1010323020 
        - Upversion to train
               - Still working thru docker image issues  >> Addressed as of Nov 15
               - Wait until official sanity with train is done to declare Milestone-3
        - Distributed Cloud
               - Testing is complete
        - Fault Containerization
               - Ada to confirm that the re-test is done
               - Ada: Testing is complete, will investigate extra task https requested by Yang
        - Intel GPU support for K8s
               - Feature is done. Ran working on one enhancement that is not considered gating.
               - Cindy/Frank to ask developer to send doc info
               - Ada to provide an update on the re-test as discussed
               - Ada: This feature is going to be retested along with Train upgrade  testing
        - Intel QAT support for K8s
               - Feature is done.
               - Cindy/Frank to ask developer to send doc into
               - Ada to provide an update on the re-test as discussed
               - Ada: This feature is going to be retested along with Train upgrade testing 

- Regression Test
        - https://docs.google.com/spreadsheets/d/1X085xI96M6PIeum87w6IEF11G-TG-W1OeGuAJWnrAWI/edit#gid=1717644237 
        - Completion Rate: 49% (up from 44%)
        - Ada to update with status, completion date, any risks, etc
        - Since we are waiting for the Train ISO. we are going to execute all the TC planned in : https://docs.google.com/spreadsheets/d/1X085xI96M6PIeum87w6IEF11G-TG-W1OeGuAJWnrAWI/edit#gid=1691167242 
        - This testing includes 100 Pytest TC + 100 Robot TC + 75 Test cases from feature testing (manual execution), and will try to cover fixed bugs. Goal , to be completed on 11/29
        - Once that we got the RC ISO we are going to start with a new Test Plan that Elio and Yang will provide + Remaining TC from first cycle that weren't executed. To be compeleted on 12/13

- Feature Test
        - https://docs.google.com/spreadsheets/d/1n9P7as4iqO55DytIRuIGdyc7x0n2WM_q-cMfHcItJlY/edit#gid=968103774 
        - Completion Rate: 100% (up from 85%)