[Starlingx-discuss] Minutes: StarlingX Release Meeting - Dec 15/202
Khalil, Ghada
Ghada.Khalil at windriver.com
Thu Dec 16 22:44:25 UTC 2021
Agenda/Minutes are posted at:
https://etherpad.openstack.org/p/stx-releases
Release Team Meeting - Dec 15 2021
stx.6.0
- Release/Feature Planning Spreadsheet: https://docs.google.com/spreadsheets/d/13p0BMlBgJXUVForOFsblAJq9jA1-FMBlmhV5TIc70IE/edit#gid=1107209846
- Test Tracking Spreadsheets: https://drive.google.com/drive/folders/1lfm073XaFGxHZSAf0RPS1DGK6QCReO9u
- r/stx.6.0 Status
- Branch: https://review.opendev.org/q/projects:starlingx+branch:r/stx.6.0
- Builds: http://mirror.starlingx.cengn.ca/mirror/starlingx/rc/6.0/centos/
- Build schedule will be on demand
- Cherry-picks: All were posted. Two left to merge
- Sanity: Starting within the next day as per Alex
- stx.6.0 Bugs
- https://bugs.launchpad.net/starlingx/+bugs?field.tag=stx.6.0
- As of Dec 15, 3 bugs are currently open.
- 2 CVEs; will not hold up the release as they can be cherrypicked later
- 1 recently tagged for openstack by a community user: https://bugs.launchpad.net/starlingx/+bug/1950406
- Test Update
- All feature testing is complete
- Ran automation regression last week. Analyzing results now.
- Pass Rate: 86.5%. Will re-run the failed TCs to rule out env issues.
- Doc Update
- Doc branch was not created as per plan
- Draft of release notes is available for review: https://review.opendev.org/c/starlingx/docs/+/820946
- Making good progress on finishing up the required reviews: https://review.opendev.org/q/project:starlingx%252Fdocs+status:open
- Target doc branch: Dec 20; otherwise will wait for early Jan. will discuss w/ doc team by email
- Blog Post Update / Release Announcement
- Release Announcement
- Prime: Ildiko
- Planned for early Jan
- Certificate Management Improvement Blog
- Prime: Ghada / Sabeel
- Info sent to Ildiko.
- Ildiko is converting it to markdown. Will create tentative pull request, but will only merge after the release announcement.
- Distributed Cloud Scalability Blog
- Prime: Ram S
- Started. Target is to provide to Ildiko by Jan 15.