[Starlingx-discuss] Release planning - reviewing stx.8.0 milestone-2 offline
Cooke, Rob
Rob.Cooke at windriver.com
Wed Oct 19 17:30:47 UTC 2022
Hi Ghada,
Updates as per the request below.
Release test plan defined - including test automation deliverables
- Action: Rob to review/confirm that this can be done by Oct 19.
[Rob] Plan has been defined, this can be closed.
- Rob, For your action:
- please review the following test milestones in [1] - worksheet: Release Milestones
- Feature Test Complete
- Regression Test Start
- Regression Test Complete
- Final Regression Complete
Suggest any date or duration changes if needed. Or confirm that the current plan is reasonable
[Rob] I have reviewed the milestones and believe the plan is reasonable.
- please review the "Feature Tested" dates for the various features in [1] - worksheet: Release Candidates
These dates were updated by the individual feature leads, so I expect they are accurate
[Rob] Agreed, given the review with feature leads, I believe these to be accurate.
- please comment on whether there are planned automation deliverables for stx.8.0
[Rob] We will plan some automation deliverables, the extent to which has not been fully defined yet
- please complete by EOD Thursday Oct 20
- I already see that you have a folder for the stx.8.0 test activities [2], so thank you!
-----Original Message-----
From: Khalil, Ghada <Ghada.Khalil at windriver.com>
Sent: Wednesday, October 19, 2022 1:02 PM
To: starlingx-discuss at lists.starlingx.io; Cooke, Rob <Rob.Cooke at windriver.com>
Subject: Release planning - reviewing stx.8.0 milestone-2 offline
Hello all,
Since the bi-weekly starlingx release planning meeting was not held this week due to the PTG, I'd like to review the stx.8.0 milestone-2 criteria offline using the mailing list. The milestone is targeted for this week and I believe we are in good shape to declare it.
The criteria for the milestone are:
- Feature plans defined and feature development well underway
- Based on the recent updates in [1] - worksheet: Release Candidates, it looks like feature leads have been updating feature dates. Thank you!
- I'd like to ask each feature lead to have a final look and make any further updates by EOD Thursday Oct 20
- Release test plan defined - including test automation deliverables
- Action: Rob to review/confirm that this can be done by Oct 19.
- Rob, For your action:
- please review the following test milestones in [1] - worksheet: Release Milestones
- Feature Test Complete
- Regression Test Start
- Regression Test Complete
- Final Regression Complete
Suggest any date or duration changes if needed. Or confirm that the current plan is reasonable
- please review the "Feature Tested" dates for the various features in [1] - worksheet: Release Candidates
These dates were updated by the individual feature leads, so I expect they are accurate
- please comment on whether there are planned automation deliverables for stx.8.0
- please complete by EOD Thursday Oct 20
- I already see that you have a folder for the stx.8.0 test activities [2], so thank you!
Please note that feature proposals are come in at any time during the release cycle provided the feature dates fit within the overall release milestones, so declaring Milestone-2 doesn't impact new feature proposals.
Regards,
Ghada
[1] https://docs.google.com/spreadsheets/d/1cjhRQm717zOTo2ngs5SEs3elhJwSRxFAI-ruqJaBe80/edit#gid=1107209846
[2] https://drive.google.com/drive/folders/1E_AQPxVrNnbVtSqQ9_CdqYidqMmYcq4n
More information about the Starlingx-discuss
mailing list