Hey Haris, Just following up with you, as Rob's delegate while he's out, What is the status of STX 9.0 Release: Regression Test Complete (including Final Regression) ... FCST was March 22 . From STX Meeting: ? Regression Test Complete (inclduing Final Regression) - Fcst: Feb 28 >> March 6 >> March 22 >> Done ? Update ? * Combining the remaining regression testing w/ the final regression on the stx.9.0 branch * Sanity has started on stx.9.0; should be done by end of this week ( March 15 ) - Update ? * Some manual regression is in progress ... should be done mid-next-week ( March 20 ) - Update ? * Plan to complete automated regression by mid-next-week ( March 20 ) -- - Update ? * Note: There is a risk to the above dates due to lab infrastructure moves * Action: Haris to confirm the above regression plan ? haris did confirm plans last week * (march 20) no update ... greg to ping haris on "Regression Test Complete" milestone status on mailing list. let us know, Greg.